Dear Team,
I have the below details in the material master
Strategy: 40 (Planning with final assembly)
Consumption Mode: 2 (Backward / Forward)
Bwd consumption Period: 40 Days
Frwd consumption Period: 40 Days
With the above material master settings, i have created the sale order for the material of qty 10 with the delivery date of 29.01.2014. Also i have created the PIR of qty 8 with the date of 29.01.2014. With this condition, if i run MRP, i am expecting that the planned order will be created for 10 qty to cater the sale order qty of 10 and also the PIR of qty 8 (type: VSF) will be disappeared from MD04. But in the MD04 output the planned order is got created only for the 8 qty and also the PIR of qty is visible in MD04.
Q1: I am expecting that the planned order of qty 10 will be created since strategy 40 will consider the sale order qty also during MRP. Am i right?
Q2: Why the PIR of qty 8 is not getting disappeared in MD04 after MRP as per the SAP Note 772856 (PIR Consumption with planning strategy)?
Thanks