Hi all,
We have a sales order bom for a configurable material (KMAT) that has two components, one of which is also configurable (KMAT). The BOM is correctly exploded when creating the sales order and the top-level material can be configured. When attempting to configure the lower-level material however, the following error message is displayed: "Item 001010 can only be changed by configuring material 123456 (item 001000)". 1010 is my lower-level item and 1000 my higher-level material (that I can successfully configure).
I would like to either configure my lower-level item independently or have the configuration values copied 1:1 using a dependency. When adding the lower-level item manually (including the link to hl-item 1000) I am able to configure both the higher and the lower-level item successfully as required.
Have found the error message online, but not been able to find a solution yet.
Thanks for your help!
KZ